Our Services ourservices arrow

Government

US EPA Superfund Site Soil Remediation

Delatte Metals Superfund Site, LA

DelatteMetalsSite

Outcome

The property was remediated of lead impacts and could be utilized for residential or other uses.

Overview

The US EPA Delatte Metals Battery Recycling Site included approximately 60,000 cubic yards of lead contaminated soil. MT2 was contracted to provide turnkey soil remediation utilizing ECOBOND® remediation technology and company services.

MT2 Services

Contaminated soil averaged approximately two feet to ten feet in depth. MT2 performed ex-situ ECOBOND® treatment of contaminated soil, allowing for disposal as a nonhazardous waste.

Community Brownfields Turnkey Remediation Project

City of Northborough, MA

NorthboroughMA

Outcome

The property was successfully remediated and redeveloped into a wetlands and park by the City of Northborough.

Overview

MT2 was contracted to perform turnkey site remediation of lead and arsenic contaminated soil and sediment in compliance with Massachusetts Department of Environmental Protection and US EPA requirements.

MT2 Services

MT2 completed turnkey site remediation including: Site preparation (erosion controls, access roads, de-watering, and installation of a temporary swale and stream diversion); Excavation of contaminated soil and sediment up to approximately 2 feet below grade; In-situ ECOBOND® remediation; Transportation and disposal to a nonhazardous landfill of treated soils; and Final site restoration including restoration of wetlands in accordance with the wetland restoration protocol and applicable permits and approvals.

County Turnkey Soil Remediation Project

Orange County, FL

OrangeCountyFL

Outcome

The County property was successfully remediated below established budget and achieved Florida DEP closure status.

Overview

Orange County, Florida required complete clean closure to residential standards of a former firing range site containing 10,000 cyds of lead contaminated soil with lead levels in excess of 25,400 ppm.

MT2 Services

MT2's turnkey firing range remediation tasks were performed in compliance with Florida DEP approved Remedial Action Plan. MT2 performed all excavation, soil processing and ECOBOND® treatment of impacted soils, placement of cleaned soils back on-site, and off-site disposal as nonhazardous waste of soils not meeting residential cleanup standards. MT2 maintained active air and storm water management to project standards.

State Government Arsenic Soil Remediation Project

Former Baldwin Metals, AZ

FormerBaldwinMetals

Outcome

The property was successfully remediated and achieved state of Arizona closure status.

Overview

MT2 performed the remediation of the former Baldwin Metals industrial site, approximately 3,000 cubic yards of contaminated soil. Surface and subsurface soils contained concentrations of arsenic (As) above Arizona Residential and Non-Residential Soil Remediation Level (R-SRL and NR-SRL, respectively) of 10 milligrams per kilogram (mg/kg). Historical soil samples collected from the Site exhibited arsenic concentrations ranging from less than 5 mg/kg to nearly 1,000 mg/kg.

MT2 Services

MT2 successfully performed turnkey remedial actions including all erosion and stringent dust control, arsenic contaminated soil treatment, sampling and analysis, and transportation and disposal of treated soils as non-hazardous waste at a Subtitle D landfill.

Federal Government Contaminated Soil Remediation Project

Denver Federal Center, CODenverFedCenter

Outcome

The property was successfully remediated and the Federal Government could utilize the property for additional office space.

Overview

MT2 was contracted to provide comprehensive soil remediation services at the Denver Federal Center Redevelopment site to meet mixed use standards.

MT2 Services

MT2 performed a treatability study which indicated that portions of the site contained elevated lead concentrations. MT2 personnel utilized proprietary ECOBOND® treatment methods and technologies to successfully treat lead impacted soils to below RCRA levels of 5.0 mg/L. This approach met federal, state, and local regulatory requirements; met and exceeded project objectives; provided significantly lower costs by employing ECOBOND®; and, met schedule requirements.

Testimonials

spd logo


Seattle Police Dept.

"Thank you for the good service – we look forward to future work with your firm in the ongoing maintenance of our ranges." Read More >

winchester logo

Winchester Ammunition

"... Their reliable staff and machinery, along with excellent planning and research make MT2 the clear choice for any organization ..." Read More >

Testimonials

nycedp logo

New York Police Department

"MT2 has successfully implemented this program and has met and exceeded all project requirements..." Read More >

suncor logo

SunCor Development Corp

"MT2 technical expertise and ECOBOND®; technologies provided substantial savings compared to alternative methods..." Read More >

Testimonials

nycedp logo

New York Police Department

"MT2 has successfully implemented this program and has met and exceeded all project requirements..." Read More >

suncor logo

SunCor Development Corp

"MT2 technical expertise and ECOBOND®; technologies provided substantial savings compared to alternative methods..." Read More >

Testimonials

nycedp logo

New York Police Department

"MT2 has successfully implemented this program and has met and exceeded all project requirements..." Read More >

suncor logo

SunCor Development Corp

"MT2 technical expertise and ECOBOND® technologies provided substantial savings compared to alternative methods..." Read More >